dbrief January 2011
dbrief Monthly January 2011
Recent awards received by Transforming Tate Modern, NEO Bankside, Thameslink Blackfriars and Better Bankside |
Flat Iron Square
NEW
Project Manager 07887 944259 |
| Introduction NEW Duration: Commenced December 2010 |
| Union Street NEW Duration: From mid-December for approximately 6 weeks |
Borough Viaduct
Thameslink Programme
Information Number: 08457 114141 |
| Corner of Borough High Street and Bedale Street November 2009 onwards |
| Road Closures: Stoney Street, Bedale Street NEW Duration: January 2011 |
| Three Crown Square UPDATED November 2009 onwards |
| Redcross Way / Park Street November 2009 onwards |
| 11-15 Borough High Street November 2009 onwards |
| Railway Approach November 2009 onwards |
NEO Bankside
Information Number: 020 7654 8600 |
| Holland St, Crane 2 Removal UPDATED Duration: Commenced Sept 2010 |
| Holland St, Street Works NEW Duration: to January 2012 |
| Concrete Frames UPDATED Until March 2011 |
| Cladding and Internal Fit Out UPDATED Until March 2011 |
| Holland Street Water Main UPDATED Duration: Commenced Sept 2010 |
Blackfriars Station
Thameslink Programme
Information Number: 08457 114141
|
| Station reopens 17 January NEW Duration: 20 November 2010 - 17 January 2011 |
| South Bank, Other track works in the area UPDATED Duration: Until mid-January 2011 |
| Equipment deliveries to site Duration: Ongoing until further notice |
Hopton Street, Constructing New South Station Entrance UPDATED |
| River Walk, Part-closure and Alternative Walking Route Duration: until late 2011 |
| Hopton Street, Reconstruction of Railway Arches Duration: Until mid-2011 |
| Night Deliveries: Blackfriars Road and Dolben Street Duration: Ongoing until further notice |
Blackfriars Railway Bridge
Thameslink Programme
Information Number: 08457 114141
|
| Stonework Repairs UPDATED Duration: Ongoing for around 2 years |
| Platform Works UPDATED Duration: Ongoing for around 2 years |
| Installing the new station roof Duration: Ongoing for around 2 years |
| Stonework Repairs Duration: Ongoing for around 2 years |
| Steelwork Repairs UPDATED Duration: Ongoing for around 2 years |
| Gritblasting Duration: Ongoing for around 2 years |
| Footway Closure on eastern side Duration: Ongoing for around 2 years |
| Other Works Duration: Ongoing for around 2 years |
Transforming Tate Modern
Information Number: 020 7401 5176 |
| Development update UPDATED Duration: hoardings until 2012 completion, demolition works until October 2010, piling works and sub-structure works until Autumn 2011 |
The Shard
Project Manager 020 3102 3726 |
| Progress Update UPDATED Duration: Spring 2012 |
London Bridge Place
Project Manager 07887 944259 |
| Demolition UPDATED Duration: to October 2011 |
| Interchange / Bus station Duration: to October 2011 |
| Southwark Council's London Bridge and Bankside development team | dbrief Quarterly Nov 2010 - Jan 2011 NEW |
Latest Photos Oct 2010 NEW |
| Responsibility for the accuracy of information published in dbrief lies with the individual contractors, developers and other companies who supply the information. Unavoidable changes to these dates may occasionally be necessary due to adverse weather conditions or other causes beyond their control. For further information, please see the contact details given for each development. | ||

| dbrief Quarterly 7< Prev | Next >dbrief December 2010 |
|---|



“Better Bankside has helped
a great deal in establishing
a safe, secure and clean
environment for me when
I set up my business here.
The rangers in particular
are an excellent deterrent
to troublemakers and can
bring in the cleaners when
we need them. That’s why we support Better Bankside.”
Kenny Lawal
Owner, Rosie Tate
Follow me