dbrief September 2011
dbrief Monthly September 2011
Borough Viaduct
Thameslink Programme
Information: 08457 114141 |
|
| 16-26 Borough High Street NEW Nov 2009 onwards |
Green Dragon Court UPDATED Nov 2009 onwards |
| Three Crown Square UPDATED Nov 2009 onwards |
Railway Approach UPDATED Nov 2009 onwards |
| Hop Exchange / Park Street UPDATED Nov 2009 onwards |
11-15 Borough High Street UPDATED Nov 2009 onwards |
| Borough High Street Bridge Launched See timelapse video + photos! |
Skanska Win Sunday Times Greenest Company |
Great Suffolk Street
Information: 020 7928 3998 |
| Project information NEW Bankside Urban Forest |
Premier Inn Hotel, Bear Lane
Contact 0741 5799579 |
Construction UPDATED |
NEO Bankside
Information: 020 7654 8600 |
|
| Final Tower Crane Removal NEW | Cladding and Internal Fit Out UPDATED Ongoing |
| Works around Holland and Sumner Streets UPDATED To Jan 2012 |
Urban Physic Garden UPDATED Now closed - see photos |
Blackfriars Station
Thameslink Programme
Information: 08457 114141 |
|
| UK Power Networks NEW |
Transport for London NEW |
Hopton Street, Constructing New South Station Entrance UPDATED |
Deliveries to site Ongoing until further notice |
| River Walk, Part-closure and Alternative Walking Route until late 2011 |
|
Blackfriars Railway Bridge
Thameslink Programme
Information: 08457 114141 |
|
| Refurbishing work UPDATED Ongoing for around 2 years |
Installing the new roof UPDATED Ongoing for around 2 years |
| Steelwork Repairs UPDATED Ongoing for around 2 years |
Footway Closure on eastern side Ongoing for around 2 years |
The Tate Modern Project
Information: 020 7401 5176 |
| Development update September 2011 NEW To 2012 |
Borough High Street Works
Thameslink Programme
Information: TFL Streets Customer Services 0845 305 1234 |
|
| One Way Resurfacing Works UPDATED End of 2011 |
Thames Water/Southern Gas Networks/UK Power |
The Place and Bus Station
Project Manager 07887 944259 (Bus Station) 07876 143330 (The Place) |
Latest UPDATED
To Oct 2011 |
The Shard
Project Manager 020 3102 3726 |
| Progress Update UPDATED To Spring 2012 |
Shakespeare's Globe
Site Manager 020 7981 9722 |
Indoor Jacobean theatre |
Flat Iron Square
Now Open |
| Complete See Photos |
![]() |
|
| London River Park | Public realm redevelopment hits new milestone @ London Bridge Quarter |
| Southwark to operate the London Permit Scheme @ Southwark Council |
Great Suffolk Street consultation event @ Bankside Urban Forest |
| Bankside House refurbishment @ LSE |
|
| Southwark Council's London Bridge and Bankside development team | dbrief Quarterly August - October 2011 |
|
| Responsibility for the accuracy of information published in dbrief lies with the individual contractors, developers and other companies who supply the information. Unavoidable changes to these dates may occasionally be necessary due to adverse weather conditions or other causes beyond their control. For further information, please see the contact details given for each development. | ||